Tour Column Footing
a Footing for a 50 level tower got poured, around 80 m^3 concrete, 40-35M dowels and 40-30M bottom Steel
the last dowels are placed

dowels for column with 90° hook sitting on bottom mat, 40 30M each way

the dowels are hold in place with a template, a 4x6 (4 inches x 6 inches, 100mm x 150mm)

concrete is coming

poured with a pump

it takes a while to pour 80m^3